Don't Let Your Velocity Dictate Your Sprint

Velocity isn't a bucket to fill. Set your sprint goal first, then use velocity to check you can reach it.

By EPiC AgileFebruary 17, 2020

Many teams let their velocity dictate their sprint. They treat velocity like a bucket: fill it with work, and once it's full, that's the sprint.

It's a common habit, and it leads to sprints that complete a lot of tasks without delivering much at all.

Watch the full tip on the EPiC Agile YouTube channel.

The problem with the bucket

When the goal of sprint planning is to fill the bucket, the team ends up with a long list of tasks. Those tasks get done, but does the sprint actually deliver something meaningful at the end? Often it doesn't, because nothing ties the work together.

Start with the sprint goal

Instead of filling the bucket, start by defining your sprint goal. What do we want to achieve this sprint, and why does it matter?

Then use velocity for what it's for: checking whether the sprint goal is achievable. That's its whole job. Velocity tells you whether you can reach the goal. It doesn't decide what goes into the sprint.

Not every task has to serve the goal, but none can block it

Your sprint backlog will contain tasks that don't contribute to the sprint goal. That's fine, because teams have other things to do as well.

The rule is that none of that other work should stop you from reaching the sprint goal. If you reach the middle of the sprint and aren't sure you'll make it, the tasks that don't serve the goal are the first ones to deprioritise. Your stand-ups are the place to make that call.

Leave room for the ice

Think of it like making a drink. If you fill the glass to the brim, there's no room for the ice.

The same goes for sprints. If you commit to your full velocity, you'll reach the middle of the sprint unable to move or change anything, because every point is already spoken for. Something always turns out bigger than expected, and things change.

Some teams find it helps to commit to around 20% less than their velocity. Starting lower gives you room to manoeuvre when work expands or priorities shift.

The short version

  1. Define your sprint goal first.
  2. Use velocity to check the goal is achievable.
  3. Deprioritise non-goal work first when the sprint gets tight.
  4. Don't fill the sprint to the brim. Leave room for change.

How we can help

Sprint goals and healthy planning habits are core to our EPiC Scrum Master and Agile Team Facilitator course. If your teams are busy but not delivering, talk to an operator.

Get the Operator Brief

A short fortnightly email for people who run things — one idea, one practical tool, one lesson from the field. No fluff.

Explore More Insights

Discover more lessons from the trenches of agile transformation.

View All Articles